OPTIMIZATION OF LIFTING-POINT POSITION IN DOUBLE-HOIST THREE-POINT LIFTING OF REINFORCED CONCRETE LONG PICKET (POST)[J]. MECHANICS IN ENGINEERING, 2005, 27(6). DOI: 10.6052/1000-0992-2005-096
Citation: OPTIMIZATION OF LIFTING-POINT POSITION IN DOUBLE-HOIST THREE-POINT LIFTING OF REINFORCED CONCRETE LONG PICKET (POST)[J]. MECHANICS IN ENGINEERING, 2005, 27(6). DOI: 10.6052/1000-0992-2005-096

OPTIMIZATION OF LIFTING-POINT POSITION IN DOUBLE-HOIST THREE-POINT LIFTING OF REINFORCED CONCRETE LONG PICKET (POST)

  • According to the field demand of reinforced concrete long picket (post) hoisting,the hoisting plan in double-hoist three-point lifting is analyzed, its mathematical model is established,and some difficult problems are solved.
  • loading

Catalog

    Turn off MathJax
    Article Contents

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return